Welcome. On this site you can view information concerning existing and future Romanian motorways.



DX12 Expressway: Craiova - Pitesti

Length: 121.18 km. Status:

Color map: Open (0%); under construction (48%); planned (52%).

DX12 is the first expressway under construction in Romania for the route Pitesti - Slatina - Craiova, with a total planned length of 121.18km.

For detailed information please choose a section from the list below:


SectionStatusOpening
I.Craiova - RobanestiUnder construction2021
II.Robanesti - SlatinaUnder constructionJun 2021
III.Slatina - ColonestiTender in progress-
IV.Colonesti - Pitesti (A1)Tender in progress-

I.Craiova - Robanesti

Status: Under construction

Length: 17.70km

Opening Date: 2021


Contractor: Tirrena Scavi SpA, cost: 358,179,480.69 RON excluding VAT. Contract signed in December 2018, design duration: 12 months, execution duration: 24 months.

Back to DX12 sections list

II.Robanesti - Slatina

Status: Under construction

Length: 39.85km

Opening Date: June 2021


The section consists of two lots:

  • Lot 1: Robanesti - Branet, 18.50km, contractor: consortium consisting of SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL - Consitrans SRL, cost: 661,452,009.54 RON excluding VAT. Contract signed in December 2018, design duration: 12 months, execution duration: 24 months.
  • Lot 2: Branet - Slatina, 21.35km, contractor: consortium consisting of SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL - Consitrans SRL, cost: 661,452,009.54 RON excluding VAT. Contract signed in December 2018, design duration: 12 months, execution duration: 24 months.


Back to DX12 sections list

III. Slatina - Colonesti

Status: Tender in progress

Length: 31.75km

Opening Date: n/a



Back to DX12 sections list

IV. Colonesti - Pitesti (A1)

Status: Tender in progress

Length: 31.81km

Opening Date: n/a



Back to DX12 sections list