130km.ro

Welcome. On this site you can view information concerning existing and future Romanian motorways.



A8 Union Motorway: Targu Mures - Iasi - Ungheni

Length: 305km. Status:

Color map: Open (0%); under construction (90%); planned (10%).

A8 Motorway, also known as Union Motorway, is a proposed motorway following the route Targu Mures - Ditrau - Poiana Largului - Targu Neamt - Pascani - Targu Frumos - Iasi - Ungheni.

For detailed information please choose a section from the list below:

SectionStatusOpening
I.Targu Mures - Miercurea NirajuluiUnder construction2027
II.Miercurea Nirajului - LeghinUnder construction2027, 2028, 2029, 2030
III.Leghin - Targu NeamtUnder construction2027
IV. Targu Neamt - Iasi - UngheniPartially under construction, remainder tendered2030
V. Ungheni BridgeUnder construction2026

I.Targu Mures - Miercurea Nirajului

Status: under construction

Length: 24.40km

Opening Date: 2027


Contractor: NUROL INSAAT VE TICARET A.S., price: RON 2.46 billion (excl. VAT), design duration: 6 months, construction duration: 24 months, contract signed in February 2024.

Back to A8 sections list

II.Miercurea Nirajului - Leghin

Status: Tender in progress

Length: 161.50km

Opening Date: 2027 for section 1b Miercurea Nirajului - Sarateni; 2028 for section 1d Joseni - Ditrau; 2029 for sections 2a Ditrau - Grinties and 2c Pipirig - Vanatori Neamt/Leghin; 2030 for sections 1c Sarateni - Joseni and 2b Grinties - Pipirig


This route is split into six sections, as follows:
  • Section 1b Miercurea Nirajului - Sarateni, 23.40km. Tender launched in April 2024. Contractor selected in May 2025: the consortium OZALTIN INSAAT TICARET VE SANAYI A.S. – INFRAVIS SRL, price: RON 2.98 billion (excl. VAT), design duration: 6 months, execution duration: 24 months. Contract signed in May 2025
  • Section 1c Sarateni - Joseni, 32.40km. Tender launched in October 2024. Contractor selected in March 2025: the consortium SA&PE CONSTRUCT SRL - TEHNOSTRADE SRL - SPEDITION UMB - EURO ASFALT, price: RON 4.94 billion (excl. VAT), design duration: 14 months, execution duration: 40 months. Contract signed in November 2025
  • Section 1d Joseni - Ditrau, 14.40km. Tender launched in October 2024. Contractor selected in July 2015: the consortium Danlin - Groma Hold - Intertranscom Impex SRL, price: RON 821 million (excl. VAT), design duration: 10 months, execution duration: 24 months. Contract signed in November 2025
  • Section 2a Ditrau - Grinties, 37.90km. Tender launched in October 2024. Contractor selected in March 2025: the consortium SA&PE CONSTRUCT SRL - TEHNOSTRADE SRL - EURO ASFALT DOO - SPEDITION UMB, price: RON 6.14 billion (excl. VAT), design duration: 14 months, execution duration: 40 months. Contract signed in March 2025
  • Section 2b Grinties - Pipirig, 34.10km. Tender launched in November 2024. Contractor selected in July 2025: the consortium SA&PE Construct SRL – Tehnostrade SRL – Spedition UMB – Euro Asfalt, price: RON 5.97 billion (excl. VAT), design duration: 14 months, execution duration: 40 months. Contract signed in October 2025
  • Section 2c Pipirig - Vanatori Neamt (Leghin) 19.30km. Tender launched in May 2024. Contractor: the consortium SA&PE Construct SRL – Spedition UMB SRL – Tehnostrade SRL – Euro-Asfalt d.o.o., price: RON 2.69 billion (excl. VAT), design and construction duration: 48 months. Contract signed in April 2025.

Back to A8 sections list

III.Leghin - Targu Neamt

Status: Under construction

Length: 29.91km

Opening Date: 2027


Contractor selected in July 2023: the consortium SA&PE CONSTRUCT SRL – SPEDITION UMB SRL – TEHNOSTRADE SRL, price: RON 1.56 billion, design duration: 6 months, construction duration: 24 months. Contract signed in September 2023.


Back to A8 sections list

IV.Targu Neamt - Iasi - Ungheni

Status: Partially under construction, Remainder tendered

Length: 88.77

Opening date: 2030 for sections 1, 3 and 4


This route is split into four sections, as follows:
  • Section 1 Targu Neamt (Motca) - Targu Frumos, 27.00km. Tender launched in January 2025. Contractor selected in April 2026: the consortium SA&PE CONSTRUCT SRL - TEHNOSTRADE SRL - SPEDITION UMB - Euro-Asfalt, cost: RON 4.87 billion (excl. VAT), design duration: 10 months, execution duration: 36 months. Contract signed in May 2026
  • Section 2 Targu Frumos - Letcani/DN28, 28.60km. Tender launched in February 2025. Contractor selected in April 2026: the consortium Danlin XXL - Groma Hold Ltd - Intertranscom Impex - Evropeiski Patishta, cost: RON 4.57 billion (excl. VAT)
  • Section 3 Letcani/DN28 - Iasi/DN24, 17.70km. Tender launched in May 2025. Contractor selected in April 2026: FCC Construccion, price: RON 3.93 billion (excl. VAT), design duration: 10 months, execution duration: 36 months. Contract signed in May 2026
  • Section 4 Iasi/DN24 - Border/Ungheni Bridge, 15.47km. Tender launched in December 2025. Contractor selected in April 2026: the consortium Itinera SPA - Saipem SPA - ICM SPA, price: RON 3.57 billion, design duration: 10 months, execution duration: 36 months. Contract signed in July 2026.
This route ends with the Ungheni Bridge (1.1km) over Prut river.


Back to A8 sections list

V.Ungheni Bridge

The Ungheni Bridge (1.1km) over Prut river.

Status: Under construction

Length: 1.1km

Opening Date: 2026


Contractor: Ness Proiect Europe SRL, contractor selected in July. Price: RON 151.68 million. Duration: 6 months for design, 18 months for execution. Contract signed in September 2024.


Back to A8 sections list

(C) 130km.ro / Back to Romanian Motorways list