Welcome. On this site you can view information concerning existing and future Romanian motorways.



A0 Motorway: Bucharest Ringroad

Length: 100.7 km. Status:

Color map: Open (64%); under construction (68%); planned (0%).

The Bucharest Ringroad has a proposed length of 100km.

The Southern part is split into three sections for which contractors were selected in April - May 2019:

  • Section 1, A2 - CF902 (Jilava), 16.9km, contractor Alsim Alarko Sanayi Tesisleri ve Ticaret AS, price 830,679,662.15 RON (excluding VAT). Contract signed in August 2019
  • Section 2, CF902 (Jilava) - DN6, 16.3km, contractor Alsim Alarko Sanayi Tesisleri ve Ticaret AS, price 750,849,942.12 RON (excluding VAT). Contract signed in March 2019. 8.7km between DN5 and DN6 opened in December 2023
  • Section 3, DN6 - A1, 17.97km, contractors Aktor SA - Euro Construct Trading SRL, price 853,422.022,52 RON (excluding VAT), execution duration: 42 months. Contract signed. The contract was taken over completely by Aktor SA.
The Northern part is split into four sections:
  • Section 1, DJ601 - DN1 (Corbeanca), 17.5km, contractor Impresa Pizzarotti - Retter Project Management, price: 815.08 Million RON excluding VAT. Duration: 12 months for design, 22 months for construction. Contract signed in September 2023
  • Section 2, DN1 (Corbeanca) - DN2 (Afumati), 19.0km, contractor: the consortium of SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price: 831,920,653.34 excluding VAT, 12 months for design, 22 months for construction. Contract signed in May 2021. 9.5km between DN1 and A3 opened in November 2023
  • Section 3, DN2 (Afumati) - DN3 (Cernica), 8.6km, contractor selected in November 2022: China Civil Engineering Construction Corporation, price 397,996,117.63 RON excluding VAT, 12 months for design, 18 months for construction. Contract signed in March 2023
  • Section 4, DN3 (Cernica) - A2, 4.47km, contractor: the consortium SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price 312.6 Million RON excluding VAT, 12 months for design, 18 months for construction. Contract signed in August 2020.

For detailed information please choose a section from the list below:

SectionStatusOpening
South: I.A2 - CF902 (Jilava)Partially open, remainder under constructionApr.2024, 2024
South: II.CF902 (Jilava) - DN6, Section 2OpenDec.2023, Apr.2024
South: III.DN6 - A1Under construction2024
North: I.DJ601 - DN1 (Corbeanca)Under construction2026
North: II.DN1 (Corbeanca) - DN2 (Afumati)Partially open, remainder under construction2023,2024
North: III.DN2 (Afumati) - DN3 (Cernica)Under construction2025
North: IV.DN3 (Cernica) - A2Under construction2024

South: I.A2 - CF902 (Jilava)

Status: 6.0km between Popesti Leordeni - CF902/Jilava open, Remainder under construction

Length: 16.9km

Opening Date: Apr. 2024 for 6.0km, 2024 for remainder



Back to A0 sections list

South: II.CF902 (Jilava) - DN6

Status: Open

Length: 16.3km

Opening Date: Dec 2023 for 10.0km, 2024 for 6.3km



Back to A0 sections list

South: III.DN6 - A1

Status: Under construction, contract signed in April 2019

Length: 17.97km

Opening Date: 2024



Back to A0 sections list

North: I.DJ601 - DN1 (Corbeanca)

Status: Under construction, contract signed in September 2023

Length: 17.5km


Opening date: 2026


Inapoi la lista tronsoane A0


North: II.DN1 (Corbeanca) - DN2 (Afumati)

Status: 9.5km between DN1 and A3 opened in November 2023, remained under construction

Length: 19.0km


Opening date: November 2023 for 9.5km between DN1 and A3, 2024 for the remainder


Inapoi la lista tronsoane A0


North: III.DN2 (Afumati) - DN3 (Cernica)

Status: Under construction

Length: 8.6km


Opening date: 2025


Inapoi la lista tronsoane A0


North: IV.DN3 (Cernica) - A2

Status: Under construction

Length: 4.47km


Opening date: 2024


Inapoi la lista tronsoane A0