130km.ro

Welcome. On this site you can view information concerning existing and future Romanian motorways.



DEx12 Expressway: Craiova - Pitesti

Length: 121.18 km. Status:

Color map: Open (89%); under construction (11%); planned (0%).

DEx12 is the first expressway under construction in Romania for the route Pitesti - Slatina - Craiova, with a total planned length of 121.18km.

For detailed information please choose a section from the list below:


SectionStatusOpening
I.Craiova - RobanestiOpenNov 2024
II.Robanesti - SlatinaOpenApr 2022, Jul 2022
III.Slatina - ColonestiOpen2023
IV.Colonesti - Pitesti (A1)Partially open, partially under constructionNov 2024, 2025

I.Craiova - Robanesti

Status: Open

Length: 17.70km

Opening Date: November 2024


Contractor: Tirrena Scavi SpA, cost: 358,179,480.69 RON excluding VAT. Contract signed in December 2018, design duration: 12 months, execution duration: 24 months. Contract canceled in December 2022. New tender launched in March 2023. New contractor selected in June 2023 - the consortium OZALTIN INSAAT TICARET VE SANAYI AS – STRADE BAUUNTERNEHMUNG SRL – VISIO CONSTRUCTION WORKS SRL, price: 439.29 million RON, execution duration: 18 months. Contract signed in August 2023.

Back to DEx12 sections list

II.Robanesti - Slatina

Status: Open

Length: 39.85km

Opening Date: April 2023 for lot 1, July 2022 for lot 2


The section consists of two lots:

  • Lot 1: Robanesti - Piatra Olt, 18.50km, contractor: consortium consisting of SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL - Consitrans SRL, cost: 661,452,009.54 RON excluding VAT. Contract signed in December 2018, design duration: 12 months, execution duration: 24 months. Opened in April 2022
  • Lot 2: Piatra Olt - Slatina, 21.35km, contractor: consortium consisting of SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL - Consitrans SRL, cost: 661,452,009.54 RON excluding VAT. Contract signed in December 2018, design duration: 12 months, execution duration: 24 months. Opened in July 2022


Back to DEx12 sections list

III. Slatina - Colonesti

Status: Open

Length: 31.75km

Opening Date: Dec. 2023


Contractor selected in June 2020: the consortium SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price: 999.41 Million RON (excluding VAT), design duration: 12 months, execution duration: 24 months. Contract signed in September 2020.


Back to DEx12 sections list

IV. Colonesti - Pitesti (A1)

Status: Partially open (Colonesti - Albota, 19km), difference under construction

Length: 31.88km

Opening Date: Nov. 2024 for section Colonesti - Albota (19km), difference scheduled for 2025


Contractor selected in June 2020 and confirmed in February 2021 and in July 2021: the consortium SA&PE Construct SRL - Spedition UMB SRL - Tehnostrade SRL, price: 617,080,915.60 Million RON (excluding VAT), design duration: 12 months, execution duration: 24 months. Contract signed in August 2021.


Back to DEx12 sections list

(C) 130km.ro / Back to Romanian Motorways list